De acordo com o Sommerville na 9ª edição em inglês do seu livro Software Engineering, o processo de elicitação e análise de requisitos envolve quatro etapas. Uma das etapas pode ser descrita da seguinte forma:


Inevitably, when multiple stakeholders are involved, requirements will conflict. This activity is concerned with defining which requirements are more important and finding and resolving requirements conflicts through negotiation. Usually, stakeholders have to meet to resolve diferences and agree on compromise requirements.


Trata-se da etapa denominada

Alternativas
Comentários
  • Prova de Inglês.

  • 3. Requirements prioritization and negotiation
     Inevitably, when multiple stakeholders are involved, requirements will conflict.
     This activity is concerned with prioritizing requirements and finding and resolving requirements conflicts through negotiation.
    Usually, stakeholders have to meet to resolve differences and agree on compromise requirements.

    from:
    https://pratieksuraana.files.wordpress.com/2017/09/unit-2-11.pdf

  • LETRA B

    "Inevitably, when multiple stakeholders are involved, requirements will conflict." - Requisitos conflitarão.
    A etapa que trata da resolução de conflito entre requisitos é a Etapa de Priorização e Negociação.